Jaipur: Work is being carried out quickly in direction of offering ingesting water to 21 districts of the state underneath PKC-ERCP. Tenders for Phase B of the primary part have been issued in order that the Bhajan Lal authorities can provide the reward of ingesting water to lakhs of individuals throughout this tenure. Five packages will likely be ready in Phase B. Where and the way will the water attain?
There is a plan to attach 21 districts throughout the subsequent 4 years by means of Bhajanlal authorities’s dream venture PKC-ERCP. For this, about Rs 40 thousand crores will likely be spent within the first part in order that lakhs of individuals can get Chambal water. Recently, the inspiration stone of three packages of the primary part was laid by the Prime Minister and instantly after that, tenders for 5 packages have been issued underneath Phase B of the primary part of the dam. Tenders will likely be opened on February 12 and after that work may also be seen on the bottom.
Mej Barrage on Mej River
Barrage will likely be constructed with capability of about 120 MQM.
Chambal water will likely be lifted from Naunera Barrage and despatched
Water will likely be despatched by constructing a 2.22 km lengthy aqueduct on Chambal river.
Water will attain Mej Barrage by means of a 150 meter vast canal.
Mej Barrage will likely be reached after touring a distance of about 25 kilometers.
The price will likely be round Rs 875 crore together with land acquisition.
Isarda to Ramgarh Dam
Water will attain Ramgarh Dam after touring a distance of about 116 kilometers.
Water will attain two elements by means of canal and three elements by means of pipeline.
About 40 km of canal and 76 km. the pipeline will stay
Pump home will likely be constructed on Isarda, Deal river and Dundh and Amanisha drains.
About 55 MQM water will likely be delivered to Ramgarh Dam.
The price will likely be round Rs 2200 crore together with land acquisition.
Bisalpur to Ajmer
Water will likely be transported by means of canal system and pipe traces
About 200 MQM water will likely be delivered to Ajmer
28 kilometer canal system and 70 kilometer ingesting water line will likely be laid
Pump home will likely be constructed on Dordi Sagar Dam and Lamba Harisingh Dam
The price will likely be round Rs 4700 crore together with land acquisition.
Isarda to Bandh Baretha (Bharatpur)
Water will likely be equipped by means of canal system to Bandh Bertha
Water will attain after touring about 190 kilometers
About 25 MQM water will likely be delivered to Bandh Baretha
Water will attain Bandh Baretha by way of Khora Chainpura.
Around 2250 tenders have been issued
Khora Chainpura to Alwar (Jaisamand Dam)
Water will attain the dam by means of canal system and pipe traces
Tunnel will likely be inbuilt three items for about eight kilometers
Canal system will likely be laid for 107 kilometers and pipeline will likely be laid for 14 kilometers.
Water will attain after touring about 130 kilometers
Tenders price about Rs 3450 crore issued
The authorities will make preparations for ingesting water within the first part. Under this, about 1200 MQM water of Chambal will likely be taken. Water will likely be transported additional by constructing pump homes at many locations together with Isarda, Bandh Baretha, Jaisamand Dam, Tordi Sagar Dam, Lamba Harisingh Dam. Water will transfer by means of the canal system and pipe traces. A tunnel may also be constructed between Isarda and Ajmer. There is a plan to ship water ahead by means of 150 meter vast canal all over the place. On the opposite hand, land acquisition motion may also be taken within the 12 months 2025 in order that the work will be accomplished on time.