This time there will probably be canal closure on Rajasthan Feeder Canal, Rajasthan gave consent to Punjab for Rs 136 crore, see this particular report

0
23
This time there will probably be canal closure on Rajasthan Feeder Canal, Rajasthan gave consent to Punjab for Rs 136 crore, see this particular report


Jaipur: This time the canal will probably be closed and relining work will probably be achieved on Rajasthan Feeder Canal. According to the Water Resources Department, the canal will probably be closed in April and May for relining. Besides, the canal on Sirhind feeder may even be closed and relined. Let us let you know that Rajasthan will get water from each the feeders and after relining, it’s anticipated to get about 3 to 4 thousand cusecs extra water.

To enhance the amount of water from Rajasthan Feeder Canal and to supply full water to the farmers sitting on the final finish, Bhajan Lal authorities will get the canal closed this time. During April to May, relining will probably be achieved on Rajasthan feeder for about 15 and a half kilometers in order that water might be elevated by 3 to 4 thousand cusecs. Farmers will get direct profit from this. On the opposite hand, Rajasthan authorities has agreed to provide Rs 136 crore to Punjab authorities for canal building.

Canal closure will probably be achieved on Rajasthan and Sirhind feeders
15 and a half km on Rajasthan feeder. Relining will occur until
It will probably be about 12 km on Sirhind feeder. relining until
Farmers sitting on the finish in 15 districts of Rajasthan will get water
Capacity of Rajasthan feeder will probably be 18500 cusecs of water.
Currently solely 11 to 12 thousand cusecs of water might be given.
Lakhs of farmers will get advantages from Hanumangarh to Jaisalmer.
Relining of Rajasthan feeder’s turret from 179000 to 496000
Relining of Sirhind feeder turret 119700 to 447927
Rs 97.55 crore authorised for relining on Rajasthan feeder
Rs 38.80 crore authorised for relining on Sirhind feeder
Rajasthan feeder canal about 21 toes deep

15 districts of the state get ingesting water and irrigation water from Rajasthan feeder. But resulting from lack of relining of the canal, there was steady scarcity of water. According to the Water Resources Department, the complete capability of Rajasthan feeder is 18500 cusecs of water, whereas at current solely 11 to 12 thousand cusecs of water might be taken. In such a scenario, the water capability is repeatedly lowering. Now, to supply advantages to the farmers, relining of Rajasthan feeder towers 179000 to 496000 and Sirhind feeder towers 119700 to 447927 will probably be achieved. In this, Rajasthan has to spend an quantity of greater than Rs 136 crore and on Tuesday itself Rajasthan has agreed to pay this quantity.

Due to relining on Rajasthan feeder, lakhs of farmers will be capable to get extra water for ingesting water and irrigation. The authorities had not blocked the canal final time on the demand of farmers. But this time there will probably be an effort to extend the water as much as 4 thousand cusecs by blocking the canal and relining in order that farmers would not have to face issues in future.



Source link

LEAVE A REPLY

Please enter your comment!
Please enter your name here