Jaipur: In view of the rising site visitors strain on Ajmer Road, NHAI is now engaged on its enlargement. NHAI is engaged on a devoted NH plan and getting ready DPR to widen this freeway and convert it into an expressway. The freeway will probably be made 8 lanes as an alternative of 6 from Jaipur to Kishangarh (90 km).
Flyovers or underpasses will probably be constructed at 10 new factors from Jaipur to Kishangarh. Traffic is repeatedly rising on this nationwide freeway. This freeway is most essential for going from Jaipur to different cities together with Ajmer, Bhilwara, Nasirabad and from these cities to Delhi. Currently, flyover work is happening on this freeway to ease site visitors motion and scale back jams. On a mean, greater than 1.50 lakh autos cross by means of this freeway day by day. NHAI Project Director Ajay Arya stated that consideration is being given to rising this freeway from 6 to eight lanes. Starting work on making DPR. After the DPR is ready, will probably be despatched to Morth. From the place additional work will probably be accomplished solely after the choice is taken. It will price greater than Rs 1 thousand crore to construct this mission. Arya says that our plan is to extend the width of this freeway and make it utterly devoted. Under this, to make sure that there isn’t any direct entry-exit of every other car on the freeway, flyovers or underpasses will probably be constructed at 10 locations from the place the connecting roads of predominant cities, cities or villages are coming. At current, the work of developing flyovers on this freeway is happening at Mokhampura, Bhankrota, Kamala Nehru Nagar and Padasoli Junction, which is within the closing stage. The work of flyovers at Mokhampura, Padasoli, and Kamla Nehru Nagar will probably be accomplished by the primary week of December. Whereas the flyover being constructed at Bhankrota intersection could take three months or extra to be constructed.
– Overlaying work of Gurgaon-Kotputli-Jaipur part 6 lane mission of NH 48 from Km 107.100 to Km 268.300 (size 161 km) is progressing at a quick tempo within the state of Rajasthan.
– The concessionaire M/s PCEPL, working for the final 12 years on the NHAI Gurgaon Kotputli-Jaipur Section 6 Lane Project, was faraway from the mission and brought over on 02.06.2022 resulting from non-compliance of the phrases of the contract.
– On this mission, overlaying on the principle freeway and repair street and the remaining work of the mission has been given to the contractor M/s Patel Infrastructure Pvt. Ltd. in two packages.
– Which presently has a complete size of 161.200 km from Rajasthan-Haryana Border to Jaipur, on which as per the contract the work of DBM overlaying has nearly been accomplished.
-And BC work has been began. Apart from this, DBM overlaying work on about 100 km of service street has been accomplished.
– The drivers who’ve been troubled by this mission for the final a number of years have now obtained reduction.
– The work of cleansing drains and development of concrete street underneath about 36 underpasses is being accomplished. Out of which concrete work on underpass of quantity 14, Anaj Mandi, Dadi Ka Phatak, Khirni Phatak has been accomplished.
– Sign boards, cat eyes and lighting are being put in on the freeway for the security of drivers. Construction of toll buildings and renovation of toll plazas of all three toll plazas of this freeway are in progress.
– Concrete work has been accomplished at junction quantity 14, which offered quite a lot of reduction from the issue of potholes and waterlogging through the rains.
– 4 no. It is proposed to assemble an underpass for clean motion of site visitors on the junction.
– 14 no. of this mission. DPR is being ready for development of 06 buildings from 04 lanes to 06 lanes and entry-exit 200 ft from the junction.
Actually, for clean stream of site visitors and prevention of black spots on this mission, development work of 09 extra buildings i.e. underpass and flyover bridge is being accomplished by M/s Pawan Kumar. The work of Dahami flyover has been accomplished and site visitors is working easily. The diversion has been repaired and site visitors is working easily. For clean stream of site visitors and prevention of black spots, 02 extra buildings are proposed at Sangteda and Manpura Machedi. After completion of those works, accidents at black spots will scale back and site visitors will stream easily.